ISF were recently commissioned to design and install a Westrup Dresser at a micronizing plant in North Yorkshire and transfer route in order to improve the cleaning of raw materials such as wheat.  

This project was extremely challenging as it required structural alterations to accommodate the Dresser and re-sheeting of the building itself.  

This project was conducted whilst production continued and only a two-day shutdown was allocated for all works to be completed.  

In order to ensure success, ISF had to closely monitor and manage Health and Safety throughout the process. 

We are very proud of our team’s patience and precision, which got these brilliant results.